Public Improvement Lien Deadline Runs from Completion and Acceptance

Public Improvement Lien Deadline Runs from Completion and Acceptance

Share This Post

Share on facebook
Share on linkedin
Share on twitter
Share on email

Lien Law Section 12 seems pretty clear but its always nice to have the Appellate Division confirm that clarity.  In Munoz Trucking Corp. v. Darcon Const. Inc. Munoz apparently filed a public improvement lien that mistakenly named Darcon as the general contractor.  The interesting detail here was that that Munoz commenced a foreclosure action on its 2011 incorrect lien and, apparently, did not learn of the deficiency until 2015.  It then corrected the lien in 2015 by filing a new lien listing the correct general contractor.   Munoz then sought to add the correct general contractor to the foreclosure action and the general contractor sough to dismiss the 2015 Lien.  The trial court denied the motion to amend and dismissed the 2015 lien.  The Second Department reversed.

Pursuant to Lien Law Section 12:

“[a]t any time before the construction or demolition of a public improvement is completed and accepted by the … public corporation, and within thirty days after such completion and acceptance”

In applying Section 12 the Appellate Division stated:

“The significant date in section 12 of the Lien Law is the completion and acceptance by the public corporation. The requirement is in the conjunctive and both branches must be met … before the time starts running”

The Court said that determining the dates of completion and acceptance was, generally, a question of fact.   Since the general contractor did not definitively establish when the project was completed and accepted, there was no basis to dismiss the lien or deny the motion to amend the foreclosure action and allow foreclosure of the 2015 lien to proceed.

Pursuant to Lien Law Section 12 a mechanic's lien on account of public improvement must be filed within thirty days of completion and acceptance of the project by the public entity.

One interesting detail missing from the reported decision is any mention of why it took Munoz almost 4 years to figure out the lien was incorrect.  Did the School Construction Authority (the public entity running the project) not tell them for four years?  Was there no discovery on this issue in the 4 years of the foreclosure action?  Regardless, it seems that Munoz may have lucked out here but its a good example of how important it is to make sure your lien is correct and you know the correct chain of contract.  Had Munoz been out of time, the lien would likely have been invalidated for this oversight that somehow stayed hidden for 4 years.

For more information about our mechanic’s lien practice click here.